Welcome To The Arramont Community Update For July

Construction continues, and we're pleased to share an update with you. Montbeliard Road Continuation The connection service order has now been accepted by Ausnet with their service provider to complete the connection in the coming 5-10 business days. We again thank the Arramont community for their patience during this time. APA Gas Easement Landscaping Works - Montbeliard Road Works are nearing completion on the southern section of Montbeliard Road with the central median set to be completed in the next 1-2 weeks. Stage 7 Reserve Public lighting works have been successfully completed. As we proceed with the electrical connections, please note that the area will be temporarily fenced off. We expect these works to be completed within the next two weeks. Following the completion of the connections, reinstatement works will commence. This will involve the replanting of trees and seeding of grassed areas to restore the surroundings. Stages 13 & 14A Road pavement works have progressed well, thanks to the favourable weather on site. Electrical and telecommunication reticulation are nearing completion, with the remaining concrete works scheduled for next week. Additionally, sewer and water testing have commenced, followed by topsoiling of nature strips and site cleanup. Stages 15, 16 & 20 The bulk earthworks for Stages 15, 16, and 20 are currently in progress and are advancing smoothly, thanks to the favourable weather conditions. These works are well resourced with ample machinery to ensure this key component of the works is completed in a timely manner. Stages 17, 18 & 19 Stage 18 detail design engineering re-submission has taken place and Stages 17 & 19 are progressing through Council review. Contractor tenders are now being received ahead of an anticipated Q3/Q4 works commencement. Community News The persistent problem of illegal rubbish dumping remains prevalent across the Whittlesea area. In response, the Arramont team is actively considering the installation of informative signage within the estate. These signs aim to provide guidance on how to report dumped rubbish, as well as address other forms of illegal activity.
Read More

Construction

Welcome To The Arramont Community Update For June

Construction at Arramont continues to progress, and we're pleased to share an update with you. Montbeliard Road Signal commissioning progresses with Council, who are working to close remaining applications for turn-out signals. We expect this to occur soon and look forward to the intersection becoming fully operational. Thank you for your patience during this time. The landscape works along the southern section of Montbeliard Rd are well underway and expect completion within the next 3-4 weeks. Stage 7 Reserve Public lighting works are now complete. Temporary fencing will remain in place as we work through electrical connection, which should be completed in the next two weeks. Stage 13 & 14A Our Contractor has made significant progress with electrical, telecommunication reticulation and concrete works. Due to unfavourable weather, road pavement progress has been slow. However, with a small break in the weather, we hope to bring the pavements to the asphalt layer over the next few days. Stages 15, 16 & 20 We're pleased to advise that earthworks have commenced on Stages 15 & 16. Stage 20 is scheduled to begin in the next few days, with the necessary fauna surveys and relocations carried out before tree felling. Stages 17, 18 & 19 Stage 18 functional engineering design is now approved, with Stages 17 & 19 progressing through Council review. Contractor tenders have been released ahead of an anticipated Q3 works commencement. Community News We are aware that there is a significant amount of rubbish being dumped illegally within the estate. We are working with the local authorities to have this cleaned up ASAP and to implement measures to prevent recurrence. We encourage the Arramont community to continue reporting offenders and dumped rubbish to the Whittlesea Council and appreciate the community's efforts in maintaining the estate's presentation. 100331 - Stage 14 - Class 2 crushed rock preparation in anticipation of asphalting Stage 14 Class 2 Image 102516 - Stage 15 & 16 - Earthworks have commenced Stage 15 & 16 Image
Read More

Construction

Welcome To The Arramont Community Update For April

Montbeliard Road Signal commissioning is nearing completion and should be operational in the coming weeks. We thank our community for their patience during this time. Landscaping works will commence next week on the southern section of Montbeliard Rd and will run for 8 weeks. Stage 7 Reserve Public lighting installation has commenced along Alicante Walk at the eastern end of the reserve. This work is expected to take 3-4 weeks. Please exercise caution around the fenced work zones during this time. Stages 13 & 14A Weather conditions have slowed the progress of road pavement works. We expect completion of base course asphalt and commencement of electrical and telecommunications trenching in the coming weeks. Stages 15, 16 & 20 Stage 15 & 20 detail engineering drawings have been approved by Council, with Stage 16 nearing approval. We are pleased to advise that a contractor has been appointed to this upcoming work. Site establishment and initial earthworks are scheduled to commence before the end of May. Stages 17, 18 & 19 The functional engineering design for Stage 18 is now approved. Stages 17 & 19 are progressing through Council review. Tender preparations are underway as we prepare to commence works in Q3. Community News We are aware that there is a significant amount of rubbish being dumped illegally within the estate. We are working with the local authorities to have this cleaned up ASAP and to implement measures to prevent recurrence. We encourage the Arramont community to continue to report offenders and dumped rubbish to the Whittlesea Council and appreciate the efforts of the community in maintaining the presentation of the estate. Stage 13 – Avignon St pavement progress
Read More

Construction

Welcome To The Arramont Community Update For March

Construction at Arramont continues to progress, and we're pleased to share an update with you. Montbeliard Rd Continuation We're looking forward to the light signals at the intersection becoming fully operational. Council are working through the final commissioning phases and we expect completion in the coming weeks. We appreciate your patience during this time. Montbeliard Rd - APA Gas Easement Landscaping Works Landscaping along the southern section of the road is scheduled to commence end of April and will run for approximately 8-10 weeks. Stage 7 Reserve We are excited that the reserve is now available for the community to enjoy. Installation of the public lighting along Alicante Walk will be ongoing throughout April, with works zones fenced off, but please continue to exercise caution around this area. Stage 13 & 14A Kerb and channel works are now complete. Road pavement works will continue to progress over the next few weeks before public lighting and electrical cabling. Stage 15, 16 & 20 Stage 15 engineering drawings have now been approved by Council, Stages 16 & 20 are also nearing approval. We will keep purchasers updated on timings for the commencement of early-stage works. Stage 17, 18 & 19 Functional and detailed engineering designs continue progressing through the Council. Tender preparation and Contractor discussion will start in May, before Q3 works commencement. Avignon St - Stage 13
Read More

Construction

Welcome To The Arramont Community Update For February

Construction at Arramont continues to progress, and we're pleased to share an update with you. Montbeliard Rd Works Public street lighting has now been energised bringing some much-needed light to the intersection. Signal energisation and commissioning is with the authorities and expected to occur imminently. Landscaping works for the southern section of the easement reserve are scheduled to commence in April and will run for approximately 8-10 weeks. Stage 7 Reserve Localised bunting protecting grass establishment in some areas of the reserve will remain a little longer. With favourable weather conditions, we expect to be able to remove the remaining establishment protections in the coming weeks. Stage 12 Titles have been issued and Settlements triggered. Congratulations to all our Stage 12 Purchaser's, we look forward to welcoming you to our community and watching your builds progress. Stage 13 & 14A Water and road crossing works are now complete, and our Contractor has progressed to the road construction phase of works. Stage 15, 16 & 20 Detail engineering drawings are progressing well through Council, and we expect approvals to be issued in the very near term. We anticipate commencement of some early stage works within the next 4 weeks. Stage 17, 18 & 19 Functional engineering designs continue to progress through Council's approval process. Detailed engineering design is well advanced in the background, with Council submission pending functional engineering approvals. Tender preparation and Contractor discussions are scheduled to start in the next month ahead of a Q3 works commencement. The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. Construction progress in Stages 13 & 14A
Read More

Construction

Welcome To The Arramont Community Update For January

Montbeliard Road We continue to progress through the signal energisation process with the Authorities and expect the intersection to be fully functioning by the end of the month. Landscape works to the southern easement are due to commence in April and run for approximately 8-10 weeks. Excitingly, Practical Completion has been issued for the north section of the reserve.With temporary fencing now removed, we look forward to seeing our community use these walking paths and exercise stations. Stage 12 We are pleased to advise that Council Practical has now been awarded. Titles are expected for early March, with settlements to follow soon after. Separate communication will be issued to all Stage 12 Purchasers with further updates. Stage 13 & 14A Sewer and drainage works are complete, with road boxing and crossings well advanced in both stages. Pavement works will commence next week. Stage 7 Reserve Some of the grass establishment protections around the reserve are expected for removal in the next coming weeks. Stage 15, 16 & 20 We’re in the final stage of discussions with contractors on the tender packages. Bulk earthworks plans are approved, and preliminary works will commence in March. Stage 17, 18 & 19 Functional and detailed engineering designs remain with Council for assessment and approval. Tender preparation and Contractor discussions will begin shortly ahead of Q3 works commencement. The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. Tap the link below to read the full update. 100211 - Stage 12 – Riesling St in preparation for Council Practical Completion inspection. 111559 – Stage 14 – Chenin St service road crossings completed, ready for road pavement to commence.
Read More

Construction

Welcome To The Arramont Community Update For November

Construction at Arramont continues to progress, and we’re pleased to share an update with you. Montbeliard Road We’re pleased to advise that the civil works program is complete, and Montbeliard Rd is now open for public use under a temporary traffic management arrangement. Residents will now have access to Jardin Rd through to Chenin St. We’re working with the Transport Department through the signal energisation process and anticipate full operation of the intersection sometime in January. A Council Practical Completion walk-through for the northern gas easement section is scheduled for December 9th. Subject to Council approval, temporary fencing will be removed, and the reserve will open for public use. Landscaping for the southern section of Montbeliard Rd is scheduled to commence in February and will run for approximately 8 weeks. We’re also pleased to confirm the installation of the Arramont Estate entry feature. Stage 12 Pleasingly, improved weather conditions in the past two weeks have assisted in drying out the road pavements and progressing them to pass Council proof roll. Crushed rock layers have been placed, and the base course asphalt commenced, with completion expected before the Christmas shutdown period. Upon our Contractors' return in January, wearing course and line marking are due for completion followed by remaining authority approvals ahead of Practical Completion of Works and Statement of Compliance. Stage 13 & 14A With sewer works now complete and drainage works significantly advanced, road boxing has commenced in Stage 14 and will continue into Stage 13 after the Christmas break. Stage 7 Reserve With the park now open, we encourage the Arramont community to come and check it out. Some minor works are still being conducted, so please watch out for any fenced-off areas during this time. A big thanks to all those that attended our park opening and community day. It was fantastic to see such an excellent turnout for the event and everyone enjoying the new facilities. We look forward to holding more of these events in the future. Stage 15, 16 & 20 We’re in the final stage of discussions with contractors on the tender packages. Bulk earthworks plans have been approved by Council, allowing preliminary works to commence in early 2023. Functional and detailed engineering designs are steadily advancing through the approval process with Council. Stage 17, 18 & 19 Functional and detailed engineering designs remain with Council for assessment and approval. The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. We encourage buyers to check the full construction update below for all the latest information. Montbeliard Rd looking north to Jardin Rd intersection Stage 12 base course asphalt laid in Riesling St
Read More

Construction

Check out the Waterway at Arramont

The new Waterway at Arramont is complete! Watch the time-lapse to see how the construction unfolded. Expanding across 1.26ha, this waterway not only features as a key treatment space for Melbourne Water but is also a central element of the growing Arramont community. With an 18m boardwalk for all to enjoy, as well as over 100 additional trees have been planted, make it your next walking destination!
Read More

Register Your Interest Today

Looking for land for sale to build your dream home in Wollert? Register your interest to stay up to date with sales releases and community news at Arramont estate.

Register Your Interest Today

Looking for land for sale to build your dream home in Wollert? Register your interest to stay up to date with sales releases and community news at Arramont estate.