Construction
Welcome To The Arramont Community Update For April
Montbeliard Road
Signal commissioning is nearing completion and should be operational in the coming weeks. We thank our community for their patience during this time.
Landscaping works will commence next week on the southern section of Montbeliard Rd and will run for 8 weeks.
Stage 7 Reserve
Public lighting installation has commenced along Alicante Walk at the eastern end of the reserve. This work is expected to take 3-4 weeks. Please exercise caution around the fenced work zones during this time.
Stages 13 & 14A
Weather conditions have slowed the progress of road pavement works. We expect completion of base course asphalt and commencement of electrical and telecommunications trenching in the coming weeks.
Stages 15, 16 & 20
Stage 15 & 20 detail engineering drawings have been approved by Council, with Stage 16 nearing approval. We are pleased to advise that a contractor has been appointed to this upcoming work. Site establishment and initial earthworks are scheduled to commence before the end of May.
Stages 17, 18 & 19
The functional engineering design for Stage 18 is now approved. Stages 17 & 19 are progressing through Council review. Tender preparations are underway as we prepare to commence works in Q3.
Community News
We are aware that there is a significant amount of rubbish being dumped illegally within the estate.
We are working with the local authorities to have this cleaned up ASAP and to implement measures to prevent recurrence.
We encourage the Arramont community to continue to report offenders and dumped rubbish to the Whittlesea Council and appreciate the efforts of the community in maintaining the presentation of the estate.
Stage 13 – Avignon St pavement progress