Welcome To The Arramont Community Update For January
Montbeliard Road
We continue to progress through the signal energisation process with the Authorities and expect the intersection to be fully functioning by the end of the month.
Landscape works to the southern easement are due to commence in April and run for approximately 8-10 weeks.
Excitingly, Practical Completion has been issued for the north section of the reserve.With temporary fencing now removed, we look forward to seeing our community use these walking paths and exercise stations.
Stage 12
We are pleased to advise that Council Practical has now been awarded. Titles are expected for early March, with settlements to follow soon after. Separate communication will be issued to all Stage 12 Purchasers with further updates.
Stage 13 & 14A
Sewer and drainage works are complete, with road boxing and crossings well advanced in both stages. Pavement works will commence next week.
Stage 7 Reserve
Some of the grass establishment protections around the reserve are expected for removal in the next coming weeks.
Stage 15, 16 & 20
We’re in the final stage of discussions with contractors on the tender packages. Bulk earthworks plans are approved, and preliminary works will commence in March.
Stage 17, 18 & 19
Functional and detailed engineering designs remain with Council for assessment and approval.
Tender preparation and Contractor discussions will begin shortly ahead of Q3 works commencement.
The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. Tap the link below to read the full update.
100211 - Stage 12 – Riesling St in preparation for Council Practical Completion inspection.
111559 – Stage 14 – Chenin St service road crossings completed, ready for road pavement to commence.