Construction
Welcome To The Arramont Community Update For November
Construction at Arramont continues to progress, and we’re pleased to share an update with you.
Montbeliard Road
We’re pleased to advise that the civil works program is complete, and Montbeliard Rd is now open for public use under a temporary traffic management arrangement. Residents will now have access to Jardin Rd through to Chenin St. We’re working with the Transport Department through the signal energisation process and anticipate full operation of the intersection sometime in January.
A Council Practical Completion walk-through for the northern gas easement section is scheduled for December 9th. Subject to Council approval, temporary fencing will be removed, and the reserve will open for public use.
Landscaping for the southern section of Montbeliard Rd is scheduled to commence in February and will run for approximately 8 weeks.
We’re also pleased to confirm the installation of the Arramont Estate entry feature.
Stage 12
Pleasingly, improved weather conditions in the past two weeks have assisted in drying out the road pavements and progressing them to pass Council proof roll. Crushed rock layers have been placed, and the base course asphalt commenced, with completion expected before the Christmas shutdown period.
Upon our Contractors' return in January, wearing course and line marking are due for completion followed by remaining authority approvals ahead of Practical Completion of Works and Statement of Compliance.
Stage 13 & 14A
With sewer works now complete and drainage works significantly advanced, road boxing has commenced in Stage 14 and will continue into Stage 13 after the Christmas break.
Stage 7 Reserve
With the park now open, we encourage the Arramont community to come and check it out. Some minor works are still being conducted, so please watch out for any fenced-off areas during this time.
A big thanks to all those that attended our park opening and community day. It was fantastic to see such an excellent turnout for the event and everyone enjoying the new facilities. We look forward to holding more of these events in the future.
Stage 15, 16 & 20
We’re in the final stage of discussions with contractors on the tender packages. Bulk earthworks plans have been approved by Council, allowing preliminary works to commence in early 2023. Functional and detailed engineering designs are steadily advancing through the approval process with Council.
Stage 17, 18 & 19
Functional and detailed engineering designs remain with Council for assessment and approval.
The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. We encourage buyers to check the full construction update below for all the latest information.
Montbeliard Rd looking north to Jardin Rd intersection
Stage 12 base course asphalt laid in Riesling St
Publish date