October Construction Update

Welcome to the Arramont Community Update for October.
During September, a statewide construction shutdown forced all civil development works across the state to a halt. However, the team at Arramont is working closely with our civil partner to ensure the impact on Arramont and our stages are impacted as limited as possible.
Good news for Stage 8 North, which has now been titled. Your block is now ready for you to settle and start building your dream home, congratulations!
Stage 9 continues to see minor rectification works occur and a Council Practical Completion inspection has been completed.
Road curbs and channels have been completed in Stage 10, the team is now working to install electric and telecommunication services.
Stage 11 has quickly progressed to phase 6 of construction, in which the footpaths and nature strips are being constructed.
Stage 12 is still progressing with early earthworks, meaning we're preparing the site for your future dream home.
For all title updates, please visit the construction portal here.
The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. We encourage buyers to check the construction update for the latest information.