Welcome to the Arramont Community Update for March.

We are back this month with another update on the progress at Arramont.
APA gas protection works on Montbelliard Road have reached completion, with head Contractor, Winslow, taking back ownership of the site in readiness to complete the remaining section of Montbelliard Road through to the Jardin Road intersection. Final road works are estimated to be completed in late May, before undergoing Practical Completion and handover with the Council and the Department of Transport.
Civil landscaping works on Stage 7 local park are moving rapidly, anticipated completion and handover to Council is expected by the end of October.
After some delays in Stage 10, we now have the final asphalt layer to be laid, followed by topsoil and clean up. Sewer & water main testing and electrical pre-audits are commencing in preparation for Practical Completion.
The remaining sewer and drainage works are nearing completion for Stage 12, with works to commence on road boxing and water and gas mains.
Functional engineering plan approvals for Stage 13 & 14a are anticipated over the next few weeks, with first round detail design submissions prepared and Council submission pending functional approvals.
For Stage 15, 16 and 20, the functional engineering plans are currently with Council for review, and our engineers continue to progress detail design concurrently in the background.
The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. We encourage buyers to check construction updates for all the latest information.