Welcome to the Arramont Community Update for October.
09.10.2020

With the weather warming up, things have been heating up at Arramont. The landscape works in Stage 4, 6 & 7 are now all completed and the waterway in Stage 3 is 95% complete. We are hoping the grass can establish in the waterway to allow access as soon as the sun starts shining.
The construction of Montbeliard and the installation of Melbourne Water drainage has continued. Gas works will be commencing during October.
Stages 8 & 9 internal works again have seen the sewer works continue. Once completed, the installation of Melbourne Water drainage will commence.
Stages 10 & 11 have commenced planning and approval, which will now see construction commence during October.