Construction Update October

Spring has certainly sprung at Arramont. Stages 1 and 2 has seen the landscape reserves nearing completion, along with some of the first homes which is exciting.
After passing final council inspection and with Stage 3 titles delivered, we are excited to welcome our newest residents to Arramont! Stage 3 landscaping and tree planting is to commence later this month.
This week, Stage 4 is in full swing. The final layer of asphalt has been laid, along with signage and line- marking complete. A council inspection is scheduled for mid-October.
Stage 5 has been busy, with NBN cabling now finished. The footpath is nearing completion, and asphalt installation is scheduled to begin.
Stage 6 and 7 saw the beginning of kerb works, with trenching and electrical works to commence this month. Concrete works for footpath will take place towards the end of the month.