Welcome to the Arramont Community Update for July

Construction at Arramont continues to progress, and we’re pleased to share an update with you.
Works on Edgars Creek Wetland are ongoing. Once structure works are finalised and topsoiling is completed, landscaping can begin.
Works have commenced on the base pavement and asphalt of the Montbeliard Road extension. We anticipate the completion of civil works in late August (weather permitting) before beginning the handover process with Department of Transport.
Despite poor weather, things have continued to progress at Stage 12. Our contractor has been excellent at maintaining a flexible working program to mitigate any further delays. Concrete works (including footpaths and crossovers) have commenced, along with electrical and communication trenching and reticulation. We anticipate titles for Q4 2022.
Topsoiling, stripping and bulk earthworks have begun on Stages 13 & 14A. Titles are forecasted for the end of Q2 2023.
Streetscape landscaping is scheduled to commence next week in the recently completed Stages 10 & 11. Keep an eye out for developments!
Landscaping of the APA gas easement reserve adjacent to Montbeliard Road has commenced with rock walls, feature mounding and bollard installation complete. Concrete and topsoiling works will continue over the coming weeks.
Finally, the remaining landscaping works for the Stage 7 Reserve is near completion, with playground installation, structures, topsoiling, ground covers and tree planting now finished. Only hydroseeding and grass establishment works remain before Council handover and public opening, anticipated for mid-August.
The team at Arramont are committed to ensuring purchasers get access to their lots as soon as possible. We encourage buyers to check construction updates for all the latest information.