Construction Update - April 2021

Stage 8 completing footpaths, while final lot levelling, along with topsoiling are occurring as we speak. Line marking and street signs will be completed during April to allow the formal council inspection to also occur later this month.

Stage 8 North sees the road base being completed, along with the kerb and concrete works commencing. Resources from Stage 8 North will proceed into Stage 9.

Stage 10 is seeing the drainage continue and electrical works commence while stage 11 will see the sewer commence.

For more updates visit our website our contact our team: bit.ly/ArramontConstruction