Construction Update August
01.08.2019

Stage 1 and 2 streetscape works are now nearing completion with tree planting and turf to the front of the estate to be finalised during August.
Stage 3 has seen all footpath works complete and water testing has now commenced. The sewer testing is ongoing and electrical audit dates have been booked. The final sign off is forecast for the third week of August to allow lodgement and the issue of titles.
Stage 4 is progressing well with electrical works complete. Footpaths and topsoiling will occur during August. Stage 5 has passed the lower level road tests with kerb and electrical works to occur during this month also.
In Stage 6 and 7 the water reticulation works have been completed and the lower level road construction is now occurring.