Construction Update September

House construction in Stages 1 and 2 are well underway. The final stages of turf and landscape beautification works is currently being completed which will add a glamorous touch of Spring colour to Arramont.

Stage 3 water, sewer and electrical tests have now been signed off. The final inspection by Council is scheduled for 4th September with compliance soon to follow.

Stage 4 has the majority of asphalt laid down. Footpath and topsoiling, which began in August, is now 90 percent complete. The bio-retention areas on La Tour Boulevard is scheduled for September, with a Council Inspection to follow.

Stage 5 electrical works are in full swing, with the trenching and under-ground cabling now complete. Footpath construction has begun, with the final layer of asphalt to follow.

Stage 6 and 7 has the lower level road base completed with the Class 3 road layer to commence September. Kerb works and driveway crossovers to follow.