Construction Update November

It's full steam ahead for Arramont this month. Stages 1 to 4 have titled and we are seeing plenty of positive progress in Stages 5 to 9.

Stage 5 - All physical works have finished with service authority testing and inspections currently being undertaken for Statement of Compliance purposes.

Stages 6 & 7 - Stage 6 concrete footpath works are in progress with the balance of the pavement works to follow prior to authority inspections occurring. Stage 7 telecommunications works are scheduled to be completed this month with concrete and pavement works to follow.

Stages 8 & 9 - Stage 8 & 9 are ramping up for construction commencement prior to the Christmas break.