Community Update March 2026
Construction at Arramont continues to progress, and we’re pleased to share an update with you.
Landscaping Works
Stages 17 and 19 design documentation approvals from Council are in place with Stage 17 anticipated to go out to tender in Q2 2026.
The Ultimate Wetland landscaping works is complete and is currently on maintenance. It is anticipated that Melbourne Water will open this to the public in Q3 2027.

Stage 14C, 17, 18 & 19 - Civil Works
Stage 14 and 17 topsoil stripping is complete with bulk excavation works substantially complete. Sewer reticulation, drainage pipes and pits, water and gas services are substantially complete.
Electrical and conduit works are progressing well. Road boxing and subgrade improvement works are well underway with AG drainage and pavement works schedule for commencement in the coming weeks ahead.
Stage 18 and 19 civil works commencement is pending Council and Authority approvals, with Stage 19 being currently under the tender review process with civil package contract and award anticipated to start in Q2 2026.

Other Matters
We’d like to remind current and future residents of Arramont Estate of our shared responsibility in keeping the estate clean. Please ensure your site remains neat and tidy, and if you notice any dumped rubbish, report it via Snap, Send, Solve using the following link: www.snapsendsolve.com/report/victoria