Community Update July 2025
Welcome to the Community Update for July 2025.
Construction at Arramont continues to progress, and we’re pleased to share an update with you.
Landscaping Works
Stages 17, 18 & 19 streetscapes and reserves design documentation for Council endorsement is substantially complete, with the project anticipated to go out for tender in Q4 2025.
The Ultimate Wetland is now complete and is now on maintenance, with practical completion from Melbourne Water anticipated in August 2025. We anticipate that the Ultimate Wetland will be open to the community in Q3 2027.
*Ultimate Wetland Reserve
Stage 14C, 17, 18 & 19 - Civil Works
Stages 14C, 17, 18, and 19 are progressing well and commencement of Works is pending Council and Authority Approvals
*Stage 20 Civil Works
Other Matters
We’d like to remind current and future residents of Arramont Estate of our shared responsibility in keeping the estate clean. Please ensure your site remains neat and tidy, and if you notice any dumped rubbish, report it via Snap, Send, Solve using the following link: www.snapsendsolve.com/report/victoria